New Additional QP Contractors’ Camp at Halul
   
PROJECT BRIEF

The population of Halul is expected to reach 2000 due to increasing number of joint venture companies and a  number of planned future projects. Contractors often face logistical problems during mobilization of porta cabins to the island which ultimately result in delays to projects.The temporary camps set up by contractors often fail to maintain the safety and hygiene standards required by QP.
The objective of this project is to increase the capacity of contractors’ accommodation facility and thereby:-

1.   Eliminate setting up of contractors’ own temporary camps.

2.   Accommodate all the contractors’ personnel and QP station commuters.

3.   Increase the availability of rooms during overhaul of main storage tanks, offshore emergency and navy exercise for providing recreational facilities to contractors’ personnel.

 

CLIENT NAME
Qatar Petroleum-Offshore Projects
SCOPE OF WORK
Design & Development
To prepare, Front End Engineering Design (FEED) and Detailed Design for all the disciplines.
 
 
Site Location
Halul
Project Period
2009   2010
Project Status
Ongoing